× Digital News Videos Health & Science Lifestyle Opinion Education Columnists Moi Cabinets Arts & Culture Fact Check Podcasts E-Paper Lifestyle & Entertainment Nairobian Entertainment Eve Woman Travelog TV Stations KTN Home KTN News BTV KTN Farmers TV Radio Stations Radio Maisha Spice FM Vybez Radio Enterprise VAS E-Learning Digger Classified Jobs Games Crosswords Sudoku The Standard Group Corporate Contact Us Rate Card Vacancies DCX O.M Portal Corporate Email RMS
×
menu search
Standard Logo HEALTH
Home / Health & Science

Sh26m Jaramogi hospital ward under construction collapses

HEALTH & SCIENCEBy MACTILDA MBENYWE | 1 month ago
By MACTILDA MBENYWE | 1 month ago

 

Construction workers on site at Jaramogi Oginga Odinga Teaching and Referral Hospital medical ward whose roof caved in on February 27, 2021. [Collins Oduor, Standard]

There was a scare on Saturday after Jaramogi Oginga Odinga Teaching and Referral Hospital’s medical ward under construction collapsed.

The Sh26 million 100-bed capacity whose construction was at the Linton came down in what hospital management said could be as a result of the contractor’s recklessness.

The hospital acting Chief Executive Officer Dr George Rae said the matter has been reported to the National Construction Authority and further assured staff and patients of their safety.

“The investigations have been launched and necessary precautions in place to ensure the safety of staff and our clients."

However, no one was hurt in the Saturday mid-morning incident at the lakeside City.

The project was meant to extend ward seven and eight and increase bed capacity by 100 in the wake of the Covid-19 pandemic.

Governor Anyang Nyong'o expressed concern over the incident and ordered the County Public Works Engineers to launch a probe into the incident.

In a press release, Nyong’o directed immediate investigations with findings presented within 48 hours.

The facility’s Director of Finance and Administration Alex Ochieng described the incident as unfortunate.

Standard Digital established that on February 22, Public Works Engineers recommended the demolition of the concrete gutter section at the back of the building.

The team earmarked the section for removal and reconstruction following specifications.

Before it caved in the contractor was in the process of finishing the roof.

Patients occupying both male and female wards were being moved to a new unit.

The expansion of the ward is one of its infrastructural improvements, which aims at raising the facility’s status to level six. 

The facility serves patients from Nyanza, lower Rift Valley, and Western regions.