×
App Icon
The Standard e-Paper
Kenya’s Boldest Voice
★★★★ - on Play Store
Download App

NSSF paid Chinese firm Sh655m for Hazina construction delays

The building in Nairobi CBD was to have 39 floors but was scaled down to 15. [File, Standard]

The National Social Security Fund (NSSF) was forced to pay a Chinese contractor Sh655.7 million for stoppage of construction work at the Hazina Trade Centre in Nairobi.

This is 75 per cent of the Sh871.7 million that China Jiangxi, the contractor for the 15-floor building, demanded from NSSF, a probe by the Auditor General for the financial year ended June 2020 shows.

Get Full Access for Ksh299/Week.
Uncover the stories others won’t tell. Subscribe now for exclusive access
  • Unlimited access to all premium content
  • Uninterrupted ad-free browsing experience
  • Mobile-optimized reading experience
  • Weekly Newsletters
  • MPesa, Airtel Money and Cards accepted
Already a subscriber? Log in