Concerns raised over delay in rehabilitation of Nanyuki airstrip runway

SEE ALSO :MIA beats other airports in visitor numbers
For the year ended 2017, Auditor General Edward Ouko revealed that the standoff emanated from termination of the tender by KAA and bills presented by Doch Company, the firm that won the tender. The contractor is demanding payment for part of work done, idling equipment and cost of building the temporary runway. The reports reads: “Site instructions for construction of the temporary runway and its cost estimation were not seen in the project file and the employer also did not respond to contractor’s letters requesting for applicable rates for these works as the rates used in the contract sum could not apply since this was new scope of work.” The contractor had demanded over Sh120 million for the temporary runway. Shortest time However, according to KAA Public Relations Officer Grace Odhiambo, the agency in is negotiations with the contractor for payment of constructing temporary runway, adding that the tender would be re-advertised. “We are hoping that the negotiations will be hastened so that we can re-tender the work. We intend to take the shortest time possible to repair the runway so that it gets operational,” Ms Odhiambo said.SEE ALSO :Sh398 million airstrip facelift stalls amid row over payment
Initially, the contract period was 12 months with completion date of November 23, 2015, but after a sitting by the tender committee in November 2015, completion date was extended for nine months. A progress report dated July 31, 2016, however showed that the overall progress was at 42 per cent complete with less than a month left to end of the project in revised dates. Although the contractor gave a notice of completion of the temporary runway indicating that a part of the runway was ready for use and that the remaining section was to be completed in a month, auditor general’s report revealed that there was no communication to show its completion and its readiness for use. When The Standard visited the airfield that is nine kilometres from Nanyuki town, it found the old runway that was set for rehabilitation covered by overgrown grass, while the temporary one was in bad state. Renovation of the runway was intended to enable bigger planes land there but, according to Jamie Roberts General Manager of Tropic Air Company that runs the airstrip, even small planes have since shunned landing at the airstrip due to its poor state.SEE ALSO :Airports authority lauds EU for picking Kenya in solar project