Concern as Sh8.5 billion Kisii-Isebani road project fall 16 months behind schedule

The construction of the Sh8.5 billion Isebania-Ahero highway is 16 months behind schedule due to delayed compensation of communities affected by the project, the contractor has said.

M/s China Henan International Corporation Group Limited said the total work completed up to September 2019 is estimated at only 31.56 per cent compared to the projected 76.44 per cent. The permanent work completed is 29 per cent way below the envisaged 76.24 per cent.