Nine H. Young employees injured at Olkaria Geothermal Plant

Operations at the Olkaria power plant in Naivasha were disrupted for hours on Monday, after a steam pipe under construction burst injuring nine workers.

The incident at Olkaria V Unit I plant, raised fears over plans by the Kenya Electricity Generating (Kengen) company to add an extra 83.3mw to the national grid by end of the year could be derailed.