Court stop orders, heavy rains to delay the Sh8.5 billion Kisii-Isebani

Construction of the Sh8.5 billion Isebania-Ahero highway could be delayed further as more villagers rush to court to seek compensation for their land.

The project is already 16 months behind schedule due to what the contractor had earlier on alluded to as delayed compensation of residents affected by the project.