Group Five shares plunge on $60m claim for Ghana power project

South African engineering company Group Five. [Photo: Courtesy]

JOHANNESBURG - Shares in South African engineering company Group Five plunged more than 40 percent on Thursday after a customer’s $60.5 million compensation claim relating to the unfinished Kpone power plant in Ghana.

Group Five, which began construction of the plant in 2015 but halted work last month after Cenpower Generation Company terminated the contract for the delay-plagued project, said the Ghanaian company was seeking to recover costs to complete the project as well as alleged losses and damages.

Premium Article

Get Full Access for Ksh299/Week.

Fact-first reporting that puts you at the heart of the newsroom. Subscribe for full access.
Continue Reading  →
What you get
  • Unlimited access to all premium content
  • Ad-free browsing experience
  • Mobile-optimised reading
  • Weekly newsletters & digests
Pay via
M - PESA
VISA
Airtel Money
Secure Payments Kenya's most trusted newsroom since 1902
Support Independent Journalism

Stand With Bold Journalism.
Stand With The Standard.

Journalism can't be free because the truth demands investment. At The Standard, we invest time, courage and skills to bring you accurate, factual and impactful stories. Subscribe today and stand with us in the pursuit of credible journalism.

Pay via
M - PESA
VISA
Airtel Money
Secure Payment Kenya's most trusted newsroom since 1902