Senator Cherargei questions Bunge Towers 14-year construction period
Politics
By
Stephanie Wangari
| Apr 17, 2024
Nandi Senator Samson Cherargei is questioning the prolonged construction of Bunge Towers, which has spanned fourteen (14) years.
The lawmaker has demanded that the Parliamentary Service Commission (PSC) clarify the reasons for this delay.
During a press briefing on Wednesday, April 17, Cherargei highlighted that the construction of Bunge Towers begun in 2010, with an initial budget of Sh5.89 billion.
However, he noted that the budget was subsequently revised to Sh7.1 billion, leading to increased interest due to delayed payments and other unspecified variations, ultimately totaling Sh9.6b.
He is now seeking accountability from the PSC regarding the allocation and utilisation of these funds.
READ MORE
Pipeline politics: East Africa's joint refinery dream faces slippery path
Creative economy key to job creation, says PS Fikirini Jacobs
Beyond the Silicon Savannah: Why Africa's AI revolution must start 'mashinani'
Airtel takes on Safaricom with Sh5.6b data centre
Lokichar-Lamu crude pipeline plan still on, says Treasury
Employers warn of rising costs, urge Ruto to protect jobs
British Airways parent says Mideast war to hit annual profits
Mpesa drives growth as Safaricom hits record Sh99.7b profit
Kenya to spend nearly half of budget on debt servicing
KDC roots for creative economy, innovation and youth-led enterprise growth
"It is interesting when we compare Bunge towers with the Central Bank Pension towers that took not less than three and half years to be completed...yet it is a 27-storey and an ultra-modern building that cost Sh3billion. Therefore, compared to Bunge towers, we used an extra of Sh6 billion," he noted.
The Senator has urged the PSC to furnish relevant documents, including completion certificates, certificates of occupation, and certificates of public health. Additionally, he demands explanations regarding pending works and outstanding bills awaiting payment.
Earlier in the week, The Standard reported that Members of Parliament have started the process of moving into the up-to-the-minute offices domiciled at Bunge Towers.
According to communication by National Assembly Speaker Moses Wetang'ula, the occupation of Bunge Towers will be conducted in a phased approach; the first phase will see all MPs currently in Harambee SACCO Plaza who were allocated offices in the Tower immediately relocate to their new offices.