Government unveils new transmission line in boost for power supply
Nyanza
By
Olivia Odhiambo
| Jan 30, 2026
The government has stepped up efforts to improve power supply in South Nyanza through the launch of a 132kV transmission Sondu-Ndhiwa-Homa Bay-Awendo transmission line.
The line is expected to connect about 70,000 households across Homa Bay, Migori, and their environs.
According to Ministry officials, the new infrastructure aligns with Kenya’s push toward a 24-hour economy, enabling businesses, markets, and service providers to operate beyond daylight hours with greater confidence in electricity availability.
With this, the government expects a potential rise in national peak electricity demand as previously suppressed demand in Nyanza is unlocked, signalling renewed economic activity and growth.
Energy CS Opiyo Wandayi said it will also serve as an alternative supply path to neighbouring areas, enhancing power quality and redundancy.
READ MORE
Airtel takes on Safaricom with Sh5.6b data centre
Lokichar-Lamu crude pipeline plan still on, says Treasury
Employers warn of rising costs, urge Ruto to protect jobs
British Airways parent says Mideast war to hit annual profits
Mpesa drives growth as Safaricom hits record Sh99.7b profit
Kenya to spend nearly half of budget on debt servicing
KDC roots for creative economy, innovation and youth-led enterprise growth
Kenya, World Bank deepen irrigation push to boost food security
Wandayi said the new power line ends outages and powers economic growth.
The CS said the new capacity is expected to significantly reduce outages, support industry, and unlock new economic activity across the region.
"With ongoing and upcoming connection programmes, electrification coverage in South Nyanza and
the surrounding areas of the South Rift supplied by the line are improving by 15 percent from an average of about 40 percent to roughly 55 percent. This marks a significant expansion in access alongside reliability gains," the CS noted.
Wandayi noted that the government has framed this as a major milestone in strengthening regional grid reliability and correcting long-standing supply constraints that previously limited economic growth in parts of western Kenya.
According to the Ministry, the new line has decongested the Muhoroni to Chemosit corridor that had been operating under heavy strain.
Before energisation, Sondu supplied no power to Ndhiwa, while the Muhoroni to Chemosit line carried loads as high as 68MW - levels which were considered stressful for system stability.
"After energisation, Sondu now supplies 27MW to Ndhiwa, while the load on Muhoroni to Chemosit has reduced to 40MW, and flows between Muhoroni and Kisumu have dropped significantly, allowing electricity to be distributed more efficiently across the network," explained Wandayi.
According to the Ministry, such rebalancing reduces the risk of overloads and cascading outages, strengthening grid resilience.