Turkana wind power line to be ready in three months
News
By
Reuters
| Jun 30, 2017
A power line linking a 310 megawatt (MW) wind power plant to Kenya's national grid, delayed by landowners' compensation demands among other issues, is expected to be ready in the next three months, the energy minister said on Thursday.
Kenya relies heavily on geothermal and hydro power for its electricity, providing the bulk of the country's total 2,341 MW output. Wind power provides about 25 MW.
The construction of the 266-mile (428-km), 400-kilovolt power line from the Lake Turkana Wind Power project, running from Loiyangalani in the north to Suswa in the centre, started in November 2015 and had been due to be completed by December.
Danish wind turbine maker Vestas Wind Systems, supplier of the wind farm's 365 turbines, said this month the wind farm was ready for launch but would be idle until next year as the government had not yet installed the transmission line.
Energy and Petroleum Cabinet Secretary Charles Keter said on Thursday work was under way to get all required material for local subcontractors as Spain's Grupo Isolux Corsan, the main contractor, was having financial difficulties.
READ MORE
Top 10 countries account for 79pc of planned rooms
Oil jumps, stocks drop as Mideast war prolongs market volatility
Wuerth Kenya to close shop after 29 years
IRA takes over Trident Insurance, two others in compliance crackdown
Revealed: Why local companies are shutting down
The pipeline truth: How Museveni outfoxed Ruto into ceding control of KPC
Britam takes top honours at AKI Awards
Why apologies matter as much as fixes in digital business
"We saw the need that instead of us terminating the contract, we'd rather manage by getting the materials because the subcontractors who are working on the line are Kenyans," Keter told a news conference.
"If we get the materials within the next three months, we should complete the line from Lake Turkana all the way to Suswa," he said.
The Lake Turkana consortium consists of KP&P Africa, Aldwych International, Investment Fund for Developing Countries, Finnish Fund for Industrial Cooperation, Norwegian Investment Fund for Developing Countries, Sandpiper and Vestas.
Once completed, Google will acquire Vestas' 12.5 percent-stake in the project.