Compensation hurdles delaying Lapsset project
Counties
By
Patrick Beja and Paul Gitau
| Feb 05, 2015
Kenya: Confusion over national identification serial numbers and bank account details is among the reasons holding up compensation of landowners on the land designated for the Lamu port.
National Land Commission (NLC) Chairman Muhammad Swazuri yesterday explained that unclear personal details were to blame for the delay in releasing the money to the landowners.
The Government has set aside Sh40 billion for the construction of the first three berths for the Lamu port, a component of the Lamu Port South Sudan Ethiopia Transport Corridor (Lapsset) project.
The lawyer for the 147 landowners George Kahiu has threatened to take the matter back to court.
Mr Kahiu yesterday said he clarified on the identification of 12 people when requested to do so by Government agencies and wondered why the State was still holding up the funds.
READ MORE
Forget miraa: Discovery of minerals stirs up Meru locals
How to turn the tide against Kenyans' poor saving culture
Super-rich investors bet on Kenya amid economic gloom
Flooded petrol stations to be shut
Labour CS says 390 Kenyans died in the workplace
Coffee farmers earn Sh1b at Nairobi auction
Bungoma county secures Sh401 million to combat climate change
Unlocking the creative power of out-of-home advertising
It's a bumpy ride for e-mobility firms in bid to move past start-up phase
Deepening connections with customers through conversational messaging
"We will return to court on February 11 and request that the injunction we had secured earlier to stop the construction of the Lamu port is reinstated," Kahiu warned.
Delayed for months
He said he recently talked to Transport Principal Secretary Nduva Muli and was assured that his clients would be compensated but wondered why that is yet to materialise. The first batch of 157 landowners in the area designated for the port has been identified for compensation but the process has delayed since last year.
The Government will pay out about Sh1.3 billion to acquire land in Kililana for the facility and more in Hindi-Magogoni and Mashindwani for the port access road.
The Government has acquired the land at Sh1.5 million per acre. NLC and the Ministry of Transport are jointly handling the compensation.
Residents and leaders in Lamu have complained about long delays in the release of the funds.
Lamu West MP Julius Ndegwa said most of the issues have been sorted out and hoped the funds would be released.
"I have been following the matter with the Government and only about five per cent of the issues are being contested. We want the Government to start releasing funds for those without contested matters," Ndegwa said.
- Flooded petrol stations to be shut
- Forget miraa: Discovery of minerals stirs up Meru locals
- Super-rich investors bet on Kenya amid economic gloom
- Hiring civil servants on contract will fuel corruption, experts say
- Kenyan retailers ready to pounce as Ethiopia to open up market