AfDB Backs Kenya's geothermal expansion with Sh2.6b loan

Business
By Brian Ngugi | Jan 25, 2026
Olkaria Geothermal Power Plant in Naivasha. [File, Standard]

Kenya's drive to harness underground heat for stable, clean electricity received a boost on Thursday after the African Development Bank (AfDB) approved a $16.5 million (Sh2.64 billion) loan for a new geothermal power plant.

The financing will support the construction of the 35-megawatt OrPower Twenty-Two plant at the Menengai field, a site rich with geothermal potential located north of Nakuru, the bank said.

Geothermal energy, generated from heat deep within the earth, provides a critical source of "baseload" power for Kenya. Unlike solar or wind, which depend on weather, it can produce electricity constantly, ensuring a stable and reliable supply to the national grid.

The new plant is the third in the Menengai field's first phase. Once all three are complete, they will collectively produce 105 MW, helping to power homes and businesses with affordable, renewable energy.

"Beyond expanding generation capacity, the project will deliver affordable, sustainable baseload power at one of the lowest tariffs in the country," the AfDB said in a statement.

The project is expected to generate roughly 301 gigawatt-hours of electricity annually and will avoid an estimated 1.9 million tonnes of greenhouse gas emissions over 25 years.

Wale Shonibare, the AfDB's Director for Energy Financial Solutions, said the project showcases a successful public-private model. State-owned Geothermal Development Company drills wells and supplies steam, while private firms like OrPower Twenty-Two build and operate the power plants.

"This model delivers mutual benefits," Shonibare said, allowing the government agency to earn revenue and reinvest in further geothermal exploration.

Qi Jingwen, a director at OrPower Twenty-Two, said the support from international lenders enables deeper participation in Africa's green energy development.

The AfDB added the loan advances Kenya's goal of increasing its geothermal capacity from 940 MW to over 1,800 MW by 2030, a key part of its transition to 100 per cent clean energy.

The AfDB's financing is part of a larger $91.9 million project, with additional debt funding expected from the International Finance Corporation, the private lending arm of the World Bank.

Share this story
Kenya faces mounting pressure to wrap up China trade pact
Kenya is under growing pressure to finalise its bilateral trade agreement with China as Beijing extends zero-tariff access to African partners.
Why dignity should be at the heart of Kenya's digital lending
The article argues that dignity, fairness and consumer protection must anchor Kenya’s fast-growing digital lending sector to safeguard borrowers from exploitation.
Gulf Energy secures oil rig ahead of Lokichar project kick-off
Gulf Energy, the firm that last year took over the Turkana oil project, says it has leased an oil rig from a Middle Eastern firm that will be used to drill oil wells in Lokichar.
Big win for Ruto as court clears path for sale of key State firms
President William Ruto’s administration scored a major legal victory after the High Court declared the Privatisation Act 2025 constitutional, paving the way for the sale of key State corporations.
PwC now seeks buyers for Koko Networks assets
PwC has launched a search for buyers to acquire the business or assets of the collapsed Koko Networks Ltd, as administrators move to recover value for creditors.
.
RECOMMENDED NEWS