How stalled exit from cancelled Adani deal exposes Kenya to high claims

Business
By Macharia Kamau | Nov 23, 2026
Treasury Cabinet Secretary John Mbadi. The Ketraco-Adani deal was cancelled in November 2024 following a directive by President William Ruto. [File, Standard]

Kenya has yet to conclude the termination of the controversial deal it had made with Indian firm Adani two years after the government announced the cancellation of the contract.

Adani, in October 2024, signed a contract with the Kenya Electricity Transmission Company (Ketraco) to build three electricity transmission lines and substations through the public-private partnership (PPP) model.

The contract was, however, cancelled a month later in November 2024 following a directive by President William Ruto, who was yielding to public pressure.

New disclosures by the PPP Directorate show that the termination has not been concluded with concerns that the delay in completion of the process could result in the escalation of the amount that the company has been seeking from Kenya.

“The termination of the contract between Ketraco and Adani for the Transmission Lines project, which commenced in the 2024/25 financial year, was still ongoing as at the end of the 2025-26 financial year,” said the PPP Directorate in a new report.

Adani had bagged the contract after presenting Ketraco with a privately initiated proposal (PIP) to expand power infrastructure. In the proposal, the company would build three transmission lines of 371 km, including the 206-kilometre, 400kV Gilgil-Thika-Malaa-Konza line,  and three substations.

The projects were estimated to cost Sh95.68 billion. Adani would then operate and maintain the infrastructure for 30 years while charging electricity consumers to recoup their investments.

Ketraco – which has in the past built and operated power transmission infrastructure –  is paid what is termed wheeling charges by Kenya Power to evacuate electricity from power plants to its distribution network.

The wheeling charges are passed on to consumers.

Other than transparency concerns and failure to take the proposal through a public participation process, Kenyans also raised concerns about the impact that the arrangement would have on the cost of power, noting that the wheeling charge might be higher than what the taxpayer-funded Ketraco is paid.

The PPP Directorate had in the past report said the project was cancelled before it reached financial close, following the “disqualification of the proponent due to new information on their credibility”.

President Ruto, in his 2024 State of the Nation Address, directed the cancellation of the contract, citing new information from investigative agencies and partner nations.

Adani was, at the time, facing bribery charges in the US. The charges were dismissed in August 2026.

Kenya is expected to pay Adani Sh5 billion for the cancellation of the contract.

The stalled exit further raises fears of a repeat of Ketraco’s ongoing Sh10 billion debt crisis with Spanish contractor Instalaciones Inabensa SA.

In April 2013, Ketraco awarded Inabensa two contracts to build the 127-kilometre, 400kV Lessos–Tororo transmission line— that would link Kenya’s and Uganda’s power grids and expand the Lessos substation.

Ketraco, however, terminated the contracts in April 2016, over alleged non-performance. The Spanish firm blocked the hiring of a replacement contractor in court and also lodged a case at an arbitral tribunal.

The tribunal ruled in 2019 that Ketraco had unlawfully breached the contract and ordered it to pay Inabensa €37.37 million ( Sh5.4 billion), which the tribunal ordered would continue z a 12 per cent annual interest from the date of the award.

 Ketraco lost appeals all the way to the Supreme Court, and the debt ballooned to Sh10 billion due to the compounding interest.

An October 2026 High Court ruling has also stripped Ketraco of State immunity and cleared the way for the firm to pursue liquidation proceedings against the utility

Adani had expected to play a significant role in Kenya’s PPP space as the government had also handed JKIA to India’s Adani Airport Holdings for upgrade and expansion, but this was also cancelled following public uproar and the firm’s indictment in the US on bribery allegations.

The Adani power infrastructure project is among the four cancelled projects for which the government is set to pay the contractors for contract termination.

Share this story
Construction sector turns to cloud technology to improve business operations
Kenya’s construction sector is increasingly embracing cloud technology to improve operational efficiency, reduce equipment downtime and strengthen customer service.
How pending bills are undermining survival of women-led businesses
Delayed payments by government institutions are undermining the survival and growth of SMES.
How stalled exit from cancelled Adani deal exposes Kenya to high claims
Kenya has yet to conclude the termination of the controversial deal it had made with Adani two years after the government announced the cancellation of the contract.
Why Kenya urgently needs an industry-driven industrial policy
Kenya must fundamentally rethink how it organises its productive sectors, anticipates emerging economic opportunities and prepares its workforce for the future of work.
Kenyan banks' regional bet pays off as subsidiaries power profits
Kenya's biggest lenders are reaping the rewards of a years-long push into East and Central Africa, with regional subsidiaries driving profit growth for yet another year.
.
RECOMMENDED NEWS